ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Which of the following types of cost are relevant to making financial decisions?

A. opportunity cost

B. sunk cost

C. opportunity cost and material cost only

D. sunk cost and material cost only

E. material cost

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/04/20

It has to be C. Opportunity Cost and Material costs, as these are impacted by management actions/inactions. Sunk costs are indifferent to any routine financial decisions.

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Since question is one of financial decisions,  I prefer to go with option - C .

Mohamed Kamal
من قبل Mohamed Kamal , Cost Control Manager , China State Construction Engineering Corporation Ltd. (Egypt)

it will be (C) i think the material and opportunity cost

Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C = opportunity cost and material cost only is the correct answer. 

Sunk Cost are the cost that Project has already spent/expended which cannot be recovered.

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟