The scope baseline/project charter is prepared by the:?

 

A. Project manager, project office and functional team

B. Project manager and project office

C. Project manager, project office, functional team and project sponsor

D. Project manager, project sponsor and customer/user

E. Project manager

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/02/17
Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is D

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I think option D is appropriate.

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I feel it is option C , because Scope Baseline is worked out by Project Manager & Project / Functional Team and in case of Project Charter , a P M helps draft the charter in conjunction with the Sponsor ; Sponsor may be an End User or any body external to performing organization such as a company or a government agency or any external enterprises etc.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion - D. Project manager, project sponsor and customer/user

My answer is for option A. Project manager, project office and functional team