ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You’re managing a project that is difficult to estimate, so you don’t have a good idea of when the project will end. Which of the following?

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/09/04
Imran Ahmed
من قبل Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-D (Time & Materials Contract)

FP Fixed price contract is good for Buyer but having maximum risks for seller. That is why it is not suitable for seller to accept.

T & M is a contract in which a contractor is paid on the basis of (1) actual cost of direct labor, usually at specified hourly rates, (2) actual cost of materials and equipment usage, and (3) agreed upon fixed add-on to cover the contractor's overheads and profit.

 

 

 

 

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation.

Option D - T&M appears to be most appropriate in the absence of details of project.

 

Ghulam Farid
من قبل Ghulam Farid , Contracts Officer , Abu Dhabi Company for Onshore Petroleum Operations (ADCO)

Option D is equally sharing uncertainty for both parties. So option d is ok

Faisal Ali Syed
من قبل Faisal Ali Syed , Payments & Reconciliation Officer , United Bank Limited

Option D is the best for an unanticipated project as it will at least give the control and monitoring over the time and money involved.

mamoun mokhtar
من قبل mamoun mokhtar , general manager , albyan technical foungary

1-Analogous Estimating. This is the method of recording the hours spent on tasks and noting down the expenses of projects so when there is a similar project in the future, the records can serve as references for estimating.

2-Parametric Estimating. Without any previous records and reports of the actual number of hours spent and expenses on a similar project, the other way to do it is to find public information that is relevant to the project.

3-Bottom-Up Estimating. Meet up with people who have experiences doing the tasks and let them give the estimates for this project. They will be accountable to the estimate or budget that they have created.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟