ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

As a QS which task is most difficult? Estimation? Variation? BOQ? WHY?

<p>As a QS which task is most difficult? Estimation? Variation? BOQ? WHY?</p>

user-image
تم إضافة السؤال من قبل مستخدم محذوف‎
تاريخ النشر: 2014/11/24
ernie rodriguez
من قبل ernie rodriguez , Fire Suppression Designer/Estimator/Project Manager , Kidde Canada Inc.

estimation is the process of measuring and arithmetical computaiton to come up with a certain result usually in the form of volume or area...this yields the BOQ or the Bill of Quantities...therefore, estimation and boq are almost one and the same. Based on your question of the level of difficulty between estimation/boq vs. variation/change order...i will say estimation is the more difficult of the two simply because it has a wider scope while variation simply taking-off the materials to be added and/or deducted in a single scope of work in a specified area.

Juber Ahammed
من قبل Juber Ahammed , E&I Estmation Lead , SEPAM

Hello

Firstly question to be clearly understood, It says which task is difficult. I could say all the mentioned activities are difficult  as per its scenario, I mean when we talk about variation it depends on what basics we are requesting for variation and type of contract should be a key part. For Lump Sum jobs variation will be easy way if we did it when it compared with tendered documents and Scope of work.

For unit rate and reimbursable it only on some cases we can get variations as per site/Client requirement according with tender documents.

 When we talk about estimation, it is easy way to estimate lump sum jobs. We bid lump sum projects on the basics of drawings specification and vendor list provided by FEED contractor. So we not required to bother about technical stuff. If owner is not confident with design then they will choose to subcon for unitrate contracts which is difficult task to estimate.

 

When we talk about BOQ, Its is part of estimation and variation

 

 

Thank you

 

 

 

M Bilal Abbasi
من قبل M Bilal Abbasi , SR.QUANTITY SURVEYOR , DESIGNMEN Consulting Engineering (Pvt) Ltd, Islamabad, Pakistan.

Estimation for the most difficult task because if the estimation cost above for project then totally insert for client and company member

Aldinus Saju
من قبل Aldinus Saju , Quantity Surveyor / Estimator , Saberi Construction

Variation part is more difficult. Because the approval is risky. 

Narwin Bayon
من قبل Narwin Bayon , Quantity Surveyor / Architect Engineer , Meinhardt EPCM

For the most difficult task is Variation Because it requires a lot of Processes and Approvals.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟