You are the project manager responsible for developing a new hybrid engine for a major auto manufacturer.

 

 You are in the process of developing the project schedule and would like to access the feasibility of your project schedule under various different conditions. Which of the following scheduling techniques is the LEAST appropriate?

A. What-if scenario analysis

B. Variance analysis

C. Monte Carlo analysis

D. Simulation

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/08/28

Variance analysis, in budgeting (or management accounting in general), is a tool of budgetary control by evaluation of performance by means of variances between budgeted amount, planned amount or standard amount and the actual amount incurred/sold. Variance analysis can be carried out for both costs and revenues.

Imran Ahmed
من قبل Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-B  Variance analysis is the answer

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation.

Obiviously answer is B - Variance Analysis.

Variance Analysis is the technique used for Controlling the Scope.