a-Baselines in system configurations are often also referred to as deltas.
b-In configuration management, baselines are used to control change.
c-Project management baselines are used for performance measurement.
d- In project management, baselines help assess variance and trends.
The concept of baselines is central to an effective configuration management program; it is however, not a unique configuration management concept.
A baseline is a reference point in the software development life cycle marked by the completion and formal approval of a set of predefined work products.
Baselines are also used to identify the aggregate of software and hardware components that make up a specific release of a system.
The baseline in project management refers to the initial cost, scope and schedule of the project. The baseline functions as a measure so the project will not deviate.
Usually baseline values in PM will be:
- Original Scheduled Start and Finish Dates
- Planned Effort (may be expressed in hours)
- Planned or Budgeted Cost
It's true. Baseline is used in both disciplines. In PM it's used to track changes in scope.
Option C : project management baselines are uased for performance measurment.
Thanks
It is A .....................
Option-A Baselines in system configurations are often also referred to as deltas
statement A is not true , thanks
a) is not true. "Deltas" are deviations of actuals from baselines.
All the others can be considered true.
b-In configuration management, baselines are used to control change.