ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

For completion of a project, the critical path of the network represents_.

A.     minimum time

B.     maximum time

C.     maximum cost

D.     minimum cost.

user-image
تم إضافة السؤال من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL
تاريخ النشر: 2016/04/27
ghazi Almahadeen
من قبل ghazi Almahadeen , Project Facilitator , Jordan River Foundation

Thanks for the invite ......................... D. minimum cost.A. minimum time...

emad namdar
من قبل emad namdar , deputy of general director , Iraqi atomic energy commission- ministry of military manufacturing

Critical path represent minimum time of execution the project

Mahmoud Zaher Tarakji
من قبل Mahmoud Zaher Tarakji , مدير , أوال جاليري

............A AND ....D...............

Yahia mohamed  Amen Gad
من قبل Yahia mohamed Amen Gad , إدارة - مدرب - , سنابل الأجيال للتعليم والتدريب

Thank you for your call / a

Omar Saad Ibrahem Alhamadani
من قبل Omar Saad Ibrahem Alhamadani , Snr. HR & Finance Officer , Sarri Zawetta Company

Thanks

It is A & D................

Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

The Answer is ...A. minimum time

Wasi Rahman Sheikh
من قبل Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

Answer is option D) <<<<<<<<<<<<<<<<<<<

ASIF BE Mech IEng PMP
من قبل ASIF BE Mech IEng PMP , Projects Manager - Buildings Utilities & infrastructure , Qatar General Electricity & Water Corporation

In project management, a critical path is the sequence of project network activities which add up to the longest overall duration, regardless if that longest duration has float or not. This determines the shortest time possible to complete the project

Mohammed Abdelseed
من قبل Mohammed Abdelseed , Maintenance Operations and Technical Support Section Head , Bashayer Pipeline Company

the Answer is "B", Critical Path is the longest path in the project net work, it will be calculated based on 'AOA", AON" -Critical Path method.

Abdullah Altuwayjiri
من قبل Abdullah Altuwayjiri , PMO Analyst , Qassim University - GDPM

B.     maximum time

to be more accurate, it is the path that if any of its task get delayed by a specific time, the whole project will be delayed by the same amount of time

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

"A" minimum time,

thanks....

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟