What is best suitable Programme Schedule Logic to apply for a Fastrack Project?

user-image
تم إضافة السؤال من قبل Mustafa Mohammed , Principal Planner , Parsons International & Company LLC
تاريخ النشر: 2015/12/24
El Sayed Yousef
من قبل El Sayed Yousef , Software Projects Delivery Manager , AFiT Infomration Technology

Fast Tracking will result on increase of cost by adding more resources and reduce the dependency between activities so dependent activities relations can be removed or at least finish to start can be done with a lead (i.e. activity B can start before activity A end with few days) of course this will result on more rework. This of course needs to be done on critical paths or any other critical paths.

Mustafa Mohammed
من قبل Mustafa Mohammed , Principal Planner , Parsons International & Company LLC

Expecting specific logical answer not generic one

A soft logic or Preferential logic on the critical path is most suitable  for fast-tracking a project.