ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

How can we measure and increase labor force productivity in the construction industry in Middle East ?

Additional task::  To compare results with LP in Europe

user-image
تم إضافة السؤال من قبل Samir Salileh , Project Manager, Riyadh , Formerly @ CIMS Project Management Consultancy-looking new opportunity
تاريخ النشر: 2015/12/16
Motaz Hamza
من قبل Motaz Hamza , Operations Coordinator , KCCEC

Productivty in construction is measured interms of duration elapsed to complete a task.

For example the time taken to erect pipe sleepers or the time taken to weld joints.

 

Comparing the actual time it took to complete a task versus what was planned at the start of the project provides an indication of how effcient the workforce is.

 

There are several aspects to look at when trying to increase productivity rates including but not limited to:

1. Avalability of tools and equipments

2. Availability of raw materials

3. Mobility (manpower, tools, equipments, etc)

 

Having said that, and focusing specifically on increasing workforce productivity, a few ways to achieve that include:

1. On and off the job training. 

2. financial motivation ( perks, bonuses, etc.)

3. setting clear targets and end goals so that the work force feel the progress as they carry out the work.

Usman Islam
من قبل Usman Islam , Yard Manager , Kirtanlal Scaffolding & Formwork

Using earned value analysis and comparing Schedule performance index, the project manager can decide using planned S curve with actual S curve and manage labour with CPI

Farshad Hebatollahi
من قبل Farshad Hebatollahi , Supervisor , BSBG

Each working group should have a foreman

Foreman must be familiar with the rules and be committed to its mandate

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟