To fully appreciate the benefits of post-tensioning, it is helpful to know a little bit about concrete. Concrete is very strong in compression but weak in tension, i.e. it will crack when forces act to pull it apart. In conventional concrete construction, if a load such as the cars in a parking garage is applied to a slab or beam, the beam will tend to deflect or sag. This deflection will cause the bottom of the beam to elongate slightly.

Even a slight elongation is usually enough to cause cracking. Steel reinforcing bars (“rebar”) are typically embedded in the concrete as tensile reinforcement to limit the crack widths. Rebar is what is called “passive” reinforcement however; it does not carry any force until the concrete has already deflected enough to crack. Post-tensioning tendons, on the other hand, are considered “active” reinforcing. Because it is pre-stressed, the steel is effective as reinforcement even though the concrete may not be cracked. Post-tensioned structures can be designed to have minimal deflection and cracking, even under full load.

ADVANTAGES

There are post-tensioning applications in almost all facets of construction. In building construction, post-tensioning allows longer clear spans, thinner slabs, fewer beams and more slender, dramatic elements. Thinner slabs mean less concrete is required. In addition, it means a lower overall building height for the same floor-to-floor height. Posttensioning can thus allow a significant reduction in building weight versus a conventional concrete building with the same number of floors. This reduces the foundation load and can be a major advantage in seismic areas. A lower building height can also translate to considerable savings in mechanical systems and façade costs. Another advantage of post-tensioning is that beams and slabs can be continuous, i.e. a single beam can run continuously from one end of the building to the other. Structurally, this is much more efficient than having a beam that just goes from one column to the next. Post-tensioning is the system of choice for parking structures since it allows a high degree of flexibility in the column layout, span lengths and ramp configurations. Post-tensioned parking garages can be either stand-alone structures or one or more floors in an office or residential building. In areas where there are expansive clays or soils with low bearing capacity, post-tensioned slabs-on-ground and mat foundations reduce problems with cracking and differential settlement. Post-tensioning allows bridges to be built to very demanding geometry requirements, including complex curves, variable superelevation and significant grade changes. Post-tensioning also allows extremely long span bridges to be constructed without the use of temporary intermediate supports. This minimizes the impact on the environment and avoids disruption to water or road traffic below. In stadiums, post-tensioning allows long clear spans and very creative architecture. Post-tensioned rock and soil anchors are used in tunneling and slope stabilization and as tie-backs for excavations. Post-tensioning can also be used to produce virtually crack-free concrete for water-tanks.

Mohamed Galal Hussein Ahmed Mohamed
من قبل Mohamed Galal Hussein Ahmed Mohamed , Technical Mnager , Fast Building Contracting Co.

Thank you Mr. Al Yazouri for your useful answer, my question is mainly about using of post-tension anchor in Dams. So we can say that:Post-tensioned, and in some cases, passive rock anchors have been used for a range of applications in dam engineering. These applications include providing:◦ Resistance to overturning ,

◦ Restraint against downstream sliding ,

◦ Reinforcement of excavated abutment and other slopes ,

◦ Stabilization of thrust blocks ,

◦ Additional seismic resistance,

◦ Tying down of spillway, training wall and stilling basin structures,◦ Stabilization of plunge pools and other erosion features,

◦ Raising and/or strengthening older dams that no longer meet safety or capacity requirements.

جعفر هندي زين السقاف
من قبل جعفر هندي زين السقاف , مهندس أستشاري , مشاريع اﻻشغال العامة

Endorse Mr. Mohamed Galal answer.

Elke Woofter
من قبل Elke Woofter , Project Assistant , American Technical Associates

I think Mr. Alex Yazouri explained it very well and I have nothing to add 

Thank you for the invitation

But this question is outside the scope of my specialty

Reniel Acosta
من قبل Reniel Acosta , COST ENGINEER/STRUCTURAL DETAILER , MENAKEO CONSTRUCTION INC

to prevent dam overturning