ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

When the project manager realizes only 80% percent of the work has been completed. What kind of change request authorization should be issued?

<p><strong>A. Additional resources using the contingency fund</strong></p> <p><strong>B. Escalation approval to use contingency funding</strong></p> <p><strong>C. Team overtime to meet schedule</strong></p> <p><strong>D. Corrective action based on causes</strong></p>

user-image
تم إضافة السؤال من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
تاريخ النشر: 2015/01/03
Wolf Klaas Kinsbergen
من قبل Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

That can only be D: Corrective action based on causes

RAJ DAHIYA
من قبل RAJ DAHIYA , Senior MEP Projects Manager , Trinity Engineering Services L.L.C.

I would like to choose a combination of D & C however, if i have to choose only one option, I would go for D

Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

We have not learned any major critical path and delays. Could catch-up with

D. Corrective action based on causes

LABIB KOOLI
من قبل LABIB KOOLI , Director of the Sectoral Center for Training in Hotel Technologies at Southern Hammamet , Tunisian Vocational Training Agency (ATFP)

The correct path would be D.Corrective action based on causes

A or B or C or a combination of all may be in the corrective action plan 

it's depending on the real context

Eby Mathai
من قبل Eby Mathai , Engineering Manager , KeM Engineering Services LLC

Corrective action based on causes. I assume that the proect is on schedule and only the change shall cause delay. Still magnitude cant be judged.

Basit Ali
من قبل Basit Ali , Director of Engineering , Laverda Suites & Villas / Blue Bay Resorts

Option D

Mohamed Galal Hussein Ahmed Mohamed
من قبل Mohamed Galal Hussein Ahmed Mohamed , Technical Mnager , Fast Building Contracting Co.

D. Corrective action based on causes

MOhammed Sattar Sharif
من قبل MOhammed Sattar Sharif , Business Development Manager , Hungama Digital Media Entertainment Pvt. Ltd

D would be a bit better then other options.

I don't think there is a fixed answer to this question.

This highly depends upon the situations. Any two projects will choose a different option.

This is what I think.

Since project has gone so far, may be it's too late to apply corrective action. The execution phase is either completed or very close to complete.

The last10-15% of a project is just closeout.

Any expert comment please....

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟