Which of the following statements regarding risk register is FALSE?

A. The risk register contains the results of qualitative risk analysis, quantitative risk analysis, and risk response planning B. The risk register is a component of the project management plan C. The lowest level of the RBS can be used as the risk register

user-image
Question ajoutée par Mohamed El Sayed , Project Manager , Saudi Post
Date de publication: 2014/04/12
Nancy Refai
par Nancy Refai , Health, safety and environmental management Trainer and consultant , Freelancer

c is false

Wasim Khalil Mustafa Ali PMP®
par Wasim Khalil Mustafa Ali PMP® , Consultant , Malomatia

Risk Register is not component of Project Management Plan, it is independent document contain a list for all identified risk on the project and their characteristics

(So  B is false)

 

The result of  qualitative risk analysis and  quantitative risk analysis is probability, impact and expected value and proximity and all of those must be in risk register document also risk response categories and risk response actions must be in the risk register document

(So A true)

 

 

The lowest level of the RBS can be used as the risk register but it the  main benefit for the RBS to describe the risk categories

 

(So I will consider C true)

Raafat Sallam
par Raafat Sallam , Organizational Development and Training Consultant , Training Centers, Marketing Organizations.

Very thanks, it is good question:

A is false.

B and C are true

Turki Alhajri PMP NEBOSH
par Turki Alhajri PMP NEBOSH , EHS / HSE Manager , Tabuk Pharmaceuticals

C will be the false option 

RANVIR SINGH
par RANVIR SINGH , Sr.Engineer Electrical , Fajar Al-Khaleej Cont. &Trd. Co. WLL

Its Answer is ......C. Only C.

Mahmoud Abdulkader    Darwish
par Mahmoud Abdulkader Darwish , Consultant Bridge Engineer , Brench IDS consulting company

Same answer of Mr Raafatsallam

hossam azzam
par hossam azzam , Fast food restaurant,s manager. , alexandria-egypt

Every one have his own visions

i beleive( c) is false

MohamedAli MohamedAhmed Abdelhamid
par MohamedAli MohamedAhmed Abdelhamid , HR Manager , Yemen Dairy & Juice Industries

RBS can not ne used as risk register,  so the answer is c

koshy George
par koshy George , Sr. Manager Business Development & New projects. , BIOTECH TECHNICAL SERVICES

I think the logical answer should be  'C'.