Earned value analysis is a performance reporting tool/ technique. Which of the following best describes earned value (EV)?

A. Efficiency indicator to reflect cost performance of project B. Value of the work completed C. Portion of approved cost estimate planned to be spent D. Efficiency indicator to reflect schedule performance of project E. Total of costs incurred in performing work activity

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/05/30

The answer is Option A. However Option D is the resultant of the EV analysis against the Plan.

Hafiz Muhammad Azeem
par Hafiz Muhammad Azeem , Senior Planning Engineer , SNC-LAVALIN

A. Efficiency indicator to reflect cost performance

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Value of the work completed --------------