Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You are the project manger assigned to build the house. You have determined the dependencies between activities on the project.?

One of the activity dependencies is that the foundation of the house must be created prior to the construction of the frame which of the following is true? A. This is start-to-finish relationship B. This is an example of mandatory dependency C. This is an example of preferential logic D. This is start-to-start relationship E. This is finish-to-finish relationship

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/02/27
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. This is an example of mandatory dependency

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?