You are in the process of monitoring the various project processes and their performance. Which of the following ?

are you least concerned with during the process? A. Providing forecast to update current schedule information B. Comparing actual project performance against project management plan C. None of the choices are correct D. Assessing performance to determine whether corrective actions are necessary E. Monitoring and implementation of approved changes

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/02/06
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. None of the choices are correct