Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

A project manager is creating a report of the final status of a closed project to the stakeholders. Which of the following is NOT ?

used in a final projec report to communicate the status of a project? A. Status of deliverables B. Scope baseline C. Lessons learned D. Variance information

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/06/19
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: BExplanation: The scope baseline is not a particularly useful thing once a project's done. A baseline is what you use to measure any changes to the project - whenever there's a change, you always want to compare it against the baseline. But once the project is done, the baseline isn't necessary any more.

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?