Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Consider the following situation: The customer was given a monthly report that indicates zero schedule variance?

One of the teams members are aware of at least one milestone that has not been achieved. This missed milestone will result in an overall delay in the project. Which of the following items were not reported on adequately? A. Critical path status B. Risk analysis C. Communication plan variance D. Resource management plan E. All of the above

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/02/08
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. Critical path status ------------

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?