You are the project manger for Xylophone Phonics. It produces children's software programs that teach basic reading and math skills.?

You're performing cost estimates for your project and don't have a lot of details yet. Which of the following techniques should you use?

A. Monte Carlo analysis, because this is a modeling technique that uses simulation to determine estimates

B. Analogous estimating techniques, because this is a form of expert judgment that uses historical information from similar projects

C. Parametric modeling, because this is a form of simulation used to determine estimates

D. Bottom-up estimating techniques, because this is a form of expert judgment that uses historical information from similar projects

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/01/11
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B

Analogous estimating-also called top-down estimating-is a form of expert judgment. Analogous estimating can be used to estimate cost or time and considers historical information from previous, similar projects.