Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

In a cycle of project control , slack time refers to?

user-image
Question ajoutée par jonas ssemasaka , project manager , united mission board
Date de publication: 2017/10/06
kailas anande
par kailas anande , Senior Engineer Proposal and cost , Euro Mechanical

The amount of time that a schedule activity can be delayed

without delaying the early start of any immediately following

schedule activities.

Wael Al AAwar MBA PMP CPE
par Wael Al AAwar MBA PMP CPE , Project Controls Engineer , RA international

Slack is the amount of time that a task in a project network can be delayed without causing a delay to:

subsequent tasks ("free float")

project completion date ("total float") 

swamy kolagani
par swamy kolagani , Senior Planning Engineer , Khatib&Alami Engineering Consultants Pvt. Ltd

Slack Time refers to the amount of time the activity can be delayed without affecting the project completion Date

Karishma Ghosh
par Karishma Ghosh , Audit Assistant Manager , Ernst and Young LLP

It is the time a task can be delayed without affecting the project completion deadline.

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?