Your team is developing the risk management plan. Which tool and technique of this process is used to develop risk cost elements and schedule?

activities that will be included in the project budget and schedule?

A. Information gathering techniques

B. Planning meetings and analysis

C. Strategies for both threats and opportunities

D. Risk data quality assessment

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/09/17
Charles  Mwara
par Charles Mwara , Ride Operator Co-ordinator , Doha Festival City Timoo theme park

Answer is C

Strategies for both threats and Opportunities

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

Explanation:

Planning meetings and analysis is the only tool and technique of the Risk Management Planning Process.