As a PMP, one of your responsibilities is to ensure integrity on the project. When your personal interests are put above the interests of the?

project or when you use your influence to cause others to make decisions in your favor without regard for the project outcome, this is considered which of the following?

A. Using professional knowledge inappropriately

B. Conflict of interest

C. Culturally unacceptable

D. Personal conflict issue

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/09/11
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

Explanation:

A conflict of interest is any situation that compromises the outcome of the project or ignores the impact to the project to benefit yourself or others.