You are the project manager for a cable service provider. Your project team is researching a new service offering. They have been?

 working together for quite some time and are in the performing stage of team development. A new member has been introduced to the team. Which of the following statements is true?

A. The team will start all over again at the storming stage but quickly progress to the performing stage.

B. The team will continue in the performing stage.

C. The team will start all over again with the storming stage.

D. The team will start all over again with the forming stage.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/08/11
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: D

Explanation: The introduction of a new team member will start the formation and development of the team all over again with the forming stage.