Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

The critical path is calculated by?

A. determining which tasks have the least amount of total slack.

B. subtracting the end date of task one from the start date of task two.

C. totaling the time for all activities.

D. determining the shortest path through the network.

E. Determining which tasks have the most slack

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/07/22
Binil Paul
par Binil Paul , Senior Planning Engineer , Keo International Consultants - Qatar

option A .........................................

Aneesh Shandilya
par Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option A  

The critical path is the sequence of activities that represents the longest path through a project, which determines the shortest possible project duration

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. determining which tasks have the least amount of total slack.

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?