A document which describes how project scope will be managed and how scope changes will be integrated into the project is: (choose the best answer)?

A. A risk analysis

B. A scope management plan

C. A scope statement

D. A project plan

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/06/12
ZULFIQAR ALI
par ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

Scope Management is the collection of processes used to ensure that the project includes all the tasks required to complete the project while excluding all work which is out of scope. The Scope Management Plan details how the project scope will be defined, developed, and verified. My answer is B. 

B. A scope managment plan