Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

The amount of time that an activity can be delayed from its early start without delaying the project end date is called?

 

A. Float

B. c and b

C. Total Float

D. Negative Float

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/02/18
hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

 

 

Thank you for the invitation

 Option B. A&C

Free float is the amount of time an activity can be delayed without affecting the start time of the succeeding activity.

That is right answer

not 

Option B. C&B

يوسف دمدوم
par يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation I agree the answer b

Abdul Rehman
par Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. My answer is C

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I seem B. c and b is good answer.

Muhammad Umar Farooq
par Muhammad Umar Farooq , IT Program Leader , Petro Rabigh

The answer is C.

 

There are 2 concepts need to be clarified. Float and Total Float.

 

Float is the amount of time that an activity can be delayed from its early start without delaying the successor activity.

 

Total Float is the amount of time that an activity can be delayed from its early start without delaying the project end date.

 

To get more information on Project Management, follow the following page:

https://www.facebook.com/ProjectLife-1112296792185437

Sattar Abdulkarim  Mohamed
par Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Appreciation for the invitation. It is option A - Float.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion - B. c and b

Muhammad Asif
par Muhammad Asif , Relationship Officer OG II , FAYSAL BANK LTD

Based on the given network, what is the sum of floats of activities A, B and C (Floats A+B+C) ?

 

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Of course it is C - Total Float .

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?