Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

In a contract, the point of total assumption refers to the point where?

 

A. The customer will incur no further costs for the work the contractor performs in the completion of the contract.

B. The schedule and cost variance are zero.

C. The customer incurs the total financial responsibility for each additional dollar spent.

D. The contractor incurs the total financial responsibility for each dollar spent.

E. Both1) The contractor incurs the total financial responsibility for each dollar spent

, and2) The customer will incur no further costs for the work the contractor performs in the completion of the contract..

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/02/18
Abdul Rehman
par Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. my answer is E

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion  - Option  E   --------------

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Out of the given , option D is appropriate choice & thanks for the invite.

In reality PTA refers to " the amount above which seller bears all the loss of cost overrun " .

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?