Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

A work breakdown structure is most useful for?

 

A. determining potential delays

B. developing a cost estimate

C. scheduling the start of tasks

D. identifying individual tasks for a project

E. A and C

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/01/28

Break down of work is useful to identify required tasks and then to assess the tasks which are urgent and important.In case of time pressure it also helps to identify those tasks which can be delayed.So in my opinion E is the answer.It can also help in estimating cost of potential delays.Identification of tasks is essential but it may of no value unless these tasks are prioritise.

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Out of the given options ,option B is more appropriate.

Thanks for the invitation:

 

I think the order for most useful goes in these order 

 

First         (B)

Second   (D)

Third        (C)

Fourth      (A)

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Inmy opinion, Option E is better choice

mamoun mokhtar
par mamoun mokhtar , general manager , albyan technical foungary

there is a time when all plant will shut down all delays were reported and corrected during this agreed upon period so it is really option a for determining potential delays and correct them as well

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I seem option D-identifying individual tasks for a project is good answer.

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?