Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Bar charts are most appropriate for?

 

A. Showing slack time.

B. Comparing actual to planned performance to each activity.

C. All of the other alternatives apply.

D. Showing critical path dependencies.

E. Showing which activities can be rearranged in parallel.

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/01/28
DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. My answer is B. Comparing actual to planned performance to each activity..

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Answer is B - provided Baseline is set while scheduling the activities ; otherwise comparing actual to planned one is not possible.

Abdul Rehman
par Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. I would like to select B as my answer.

يوسف دمدوم
par يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Tink you for the invitation

My answer is for  option B

Thanks for the invitations.

 

My answer is Option B) Comparing actual....

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?