You are a project manager of ABC organization. You are estimating the project in initiation phase. What level of accuracy you can expect?

 

A. - percent to + percent

B. - percent to + percent

C. - percent to + percent

D. - percent to percent

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/01/21
DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for your invitation. My answer is option-C. percent to + percent

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

It is - 25 percent to + 75 percent which is known as ROM estimate done in project initiating stage.