Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

What is not the main purpose of a final project report?

A.  Preparing acceptance of the final product, service or result.  B.  Making stakeholders aware that the project has been closed out.  C.  Acknowledging what has been done and achieved by all contributors.  D.  If a project has been cancelled before completion: Explaining the causes.

user-image
Question ajoutée par DR MD ANWAR HOSSAIN , Moderator , bayt.com
Date de publication: 2016/10/13
Md Fazlur Rahman
par Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

The purpose of Final Project Report is to summarise and indicate the following:

  1. The project has been completed and commissioned  to serve the intended purpose
  2. To mention any deviation from the original activities /project components  and rationale for deviation thereof
  3. To mention the cost increases or decreases, if any, and rationale thereof
  4. To mention whether warranty conditions has been provided by the contractor as per contract
  5. To mention that necessary support staff /operating mechanism is in place to operate  and maintain the project.
  6. To include a recommendation for  way forward when this project  output is input to another project

 

 

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

I agree with Md. Fazlur Rahman. Thank you..................................................

Mohamed Basem Hemedh
par Mohamed Basem Hemedh , Siren Projects Eastern Region Manager , Nextel Millennium Telecom Manager

It should be used later as lessons learned for future project that may shre this project the smae scope or part from it.

Ahmed Hejazi
par Ahmed Hejazi , Projects Manager , Jadat Itqan Consulting - JIC

B.  Making stakeholders aware that the project has been closed out. 

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

I think option A is better choice

MOHAMMAD MAHMOUD HASAN AL-HASHASH
par MOHAMMAD MAHMOUD HASAN AL-HASHASH , مدير صيانه , شركة الاستراتيجي للتجاره

the correct answer is A

 

regards

hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

____________Thanks for the invitation.

I would go with option A ____________

 

محمد داود محمد محسن
par محمد داود محمد محسن , رئيس قسم مالي / رئيس قسم تدقيق داخلي / رئيس قسم حسابات / رئيس قسم محاسبة تكاليف , امانة عمان الكبرى

Thank you for the invitation

A. Preparation of the final product, service, or to accept the result.

To say whether he had been saving your warranty by the contractor under the contract

 

He said any deviation from the original components of the project activities until they are taken to ensure good execution 

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation.

I would go with option A .

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?