For a project, the following earned value data have been assessed: AC: $ 4,000,000 CV: $ -500,000 SPI: 1.12 BaC: $ 9,650,000?

What is the earned value of the project? o $3,,o $3,,o $4,,o $5,,

user-image
Question ajoutée par DR MD ANWAR HOSSAIN , Moderator , bayt.com
Date de publication: 2016/10/12
Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

Earned Value is the sum of CV + AC , i.e EV = 4,000,000 + ( - 500,000 ) = 3,500,000 $

Abdul Rehman
par Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. The answer is $ 3,500,000

Waleed Hamdy
par Waleed Hamdy , MEP PROJECTS CONTROL HEAD SECTION , AZMEEL CONTRACTING COMPANY

The Earned Value = 3500,000.00 $ 