The cost baseline is usually not changed unless?

A. the basis for the original cost estimate is found to be false and the project must be re-estimated.B. significant cost deviations have been reported and it is desired to have future cost reports be based on an “as of” date.C. the revision is the result of an approved scope change.D. the time baseline is also changed

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/09/18
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Reply -----------------------------------------

Option (C) Thee revision is the result of an approved scope change

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

Though a project may have multiple cost base lines to measure different aspects of cost performance but unless there is an approved change in the project scope cost base line is not changed, usually. So I go with option C .

Imran Ahmed
par Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-C................................................

Budget updates are changes to an approved cost baseline. These values are generally revised only in response to approved changes in project scope

sardar mardookhy
par sardar mardookhy , PMP certified Project manager , MCCI

C. could be the answer because it is approved change but A is a good option  

SHYAM MURALEEDHARAN
par SHYAM MURALEEDHARAN , Costing , NASSER S. AL HAJRI CORPORATION

Cost Base line  is the  sum of  cost estimate & contingency reserve.  if  any significant changes to these two may affect the cost base line. Base line is the bench mark to measure perfomance. Compare the values in the Base line cost and Cost fields to determine if the task is still on track within your budget.It is an approved budget usually in a time distribution format used to estimate, monitor, and control the overall cost performance of the project.

mamoun mokhtar
par mamoun mokhtar , general manager , albyan technical foungary

think it is option a mostly A. the basis for the original cost estimate is found to be false and the project must be re-estimated , but other options may have imact

Krishnan Subramanian Iyer
par Krishnan Subramanian Iyer , Asst. Vice President , Reliance Life Sciences Pvt Ltd

A. the basis for the original cost estimate is found to be false and the project must be re-estimated.B. significant cost deviations have been reported and it is desired to have future cost reports be based on an “as of” date.C. the revision is the result of an approved scope change.D. the time baseline is also changed

Ramon Bayon
par Ramon Bayon , Private practice , Private practice

Unless there are changes in scope and schedule that would be added or deleted.

Armando Codilla
par Armando Codilla , WAREHOUSE OPERATOR , Macae Rio de Janiero

Letter B - Significant and cost deviations have been reported and it is desired to have future cost reports be bassed on an "As of Date".