In resources levelling?

  (A) Total duration of project is reduced

 

(B) Total duration of project is increased

 

(C) Uniform demand of resources is achieved

 

(D) Cost of project is controlled

user-image
Question ajoutée par Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
Date de publication: 2016/08/08
Ahilan R
par Ahilan R , Scientific Assistant-D , Nuclear Power Corporation of India Ltd (NPCIL)

i endorse MD RASHID RAZA's answer

Yahya Bah
par Yahya Bah , Principal & Marketing Consultant , International Community

This is a common term used in project management. It is a technique for adjusting start and deadline dates arising from resource constraints in order allign demand to supply. 

In a nutshell, it helps in the effective coordination resources to ensure that supply meets demand in the event of constraints by adjusting deadlines.

MD RASHID RAZA
par MD RASHID RAZA , qa/qc civil engineer , Arkitechno consultant india limited

In resources levelling is a technique in which start and finish dates for any activity are adjusted in accordence with the availibility of resource and material.