2. The project manager for a construction project discovers that a new water?

line is being created in the neighborhood where he’s managing a project. Company policy requires that a series of forms for city environmental changes need to be filled out before his team can continue work on the project. This is an example of:

A) A portfolio.

B) A Program.

C) An enterprise Environmental factor

D) A Project

user-image
Question ajoutée par Nader Ali , Technical office manager , AlSafwa Contracting
Date de publication: 2016/07/28
Faraz Shafiuddin Shafiuddin
par Faraz Shafiuddin Shafiuddin , Business Analyst , National Guard Health

C)An environment enterprise factor

Mohammad Saad
par Mohammad Saad , Senior Business Analyst -Product Owner , GET Group Smart Business Solution

External Environmental Factor.

It's the answer c: An enterprise Environmental factor.

Saghir Saddiqui
par Saghir Saddiqui , Site Civil Engineer , Shafique Construction Company

C) An enterprise Environmental factor

Nader Ali
par Nader Ali , Technical office manager , AlSafwa Contracting

(please click on show detais for the full question.)

The Answer is C) An enterprise Environmental factor