In asphalt works, what should be observed at site before requesting for a delivery of Hot Mix Asphalt?

user-image
Question ajoutée par Nelio Beleo , Civil Inspector , Petrojet
Date de publication: 2016/07/14
Ahilan R
par Ahilan R , Scientific Assistant-D , Nuclear Power Corporation of India Ltd (NPCIL)

Confirm the weather, temp. of mix should be not ess than 140º Celcius at site before laying.

ensure loose particles/foregin materials removed from the laying area

Ensure all equipments are in good condition

 

Rami Joudeh
par Rami Joudeh , Senior Resident Engineer , Jacobs

Check Whether report and condition: temperature, rain, fog

 proper spreading of MC 70 without  any dust, or water

 checking the machinery maintenance record and make sure no oil leak

 proper safety condition at the site

Mohammad Hasan Annuari
par Mohammad Hasan Annuari , Project Support Engineer , Private contractor

Always watch for the weather condition, check everything you need if they are in place otherwise these will cause a delay, because the damages will be charge against you.

safety precations,weather condition,ensure clean area,all equipments are ok, then mc or rc spray.

faisal abdulgadir eisa
par faisal abdulgadir eisa , مهندس مواد , الاتحاد الهندسي السعودي (خطيب وعلمي )

1- check the compaction of subase.

2- applied and rate of mc-1

3- survyes

muhammad Iqbal
par muhammad Iqbal , Fore Man , Copri Construction Enterprises

First we should see having road level given by Surveyor then see MC spray on wet mix . See the road should be compressed. Further see the road if any place pumping dig the pumping place and ok then start the asphalt work with fever machine .

Mohammad Hasan Annuari
par Mohammad Hasan Annuari , Construction Project Manager , FLORIDABLANCA CONSTRUCTION AND DEV. CORP.

IT IS BETTER FOR YOU TO CHECK WITH THE WEATHER FIRST BEFORE REQUESTING THE HOT MIX ASPHALT. SEE TO IT THAT EVERYTHING YOU NEED ON SITE IS READY AND PREPARED OTHERWISE THE DAMAGES WILL BE CHARGE AGAINST YOU.

Amjad Razzack
par Amjad Razzack , administration manager , Safari company Ltd

Convert the tonnage into sq mtrs with required thickness.

Karthikeyan Subramanian
par Karthikeyan Subramanian , Site Supervisor , SHAPOORJI PALLONJI MIDEAST LLC

The final factor is the temperature of the hot mix asphalt (HMA) during the compaction process. ... Mix should be delivered to the paving site at a temperature of at least250°F for a Marshall ... Both compactors were observed at various times500 feet to1,000 feet behind the paver. ... 140º Celcius minimum at site before laying.

Uchenna Eze
par Uchenna Eze , Design/Project Engineer , ISAAC UDEZUE & ASSOCIATES ENUGU NIGERIA

Climatic condition, ensure the that temperature is not high....

Ensure everything thing is ready before requesting to avoid delay.

 

 

Sachin prabhakar rao
par Sachin prabhakar rao , Material Engineer , Burmah trading and Contracting Company

main factors to be considered before requesting delivery is the weather conditions . even if the HMA meets the requirements if the weather condition is worse we cannot pave the asphalt . secondly the road surface should be cleaned using a compressor to remove dust and gravel particles on the road . this should be done before mc 1 and later before paving . then comes all other factors of HMA