Which of the following control types has the highest risk to the owner?

A. Time and material (T&M)

B. Cost plus fixed fee (CPFF)

C. Cost plus incentive fee (CPIF)

D. Firm fixed price (FFP)and Time and material (T&M)

E. Firm fixed price (FFP)

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/07/08
Usman Islam
par Usman Islam , Yard Manager , Kirtanlal Scaffolding & Formwork

Option B looks best choice here. However, option C is also related because of incentive.

This is a confusable question and need a lot to explain all types.

However to just answer, i go for option 

A. Time and material (T&M)

VINAY KUMAR GOSWAMI
par VINAY KUMAR GOSWAMI , Partner , 2MI

Thanks for invite

Option - B (Owner can not control the costs of service provider. Additionally service provider has not incentive to keep costs in check or reduce the costs as he will get the same fixed fee).

T&M is risky proposition too. However owner has control over the resources, scope and budget. Hence it is less risky when compared with CPFF.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The best choice is

A. Time and material (T&M)

Ksenija Kancelak
par Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My opinion is that the right answer is:

 

A. Time and material (T&M)

Md Fazlur Rahman
par Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

OPTION-C is correct choice

Cost plus incentive is the most risky as the owner does not have any control on cost(material, labor charge) and the contractors incentive will be more when the cost increases.

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Appropriate answer is C .

In case of C , in order to get more incentive which is based on cost, vender or seller can jack-up the cost. Hence Owner is at high cost risk.

Whereas Time & Material is used for small value and short time contracts.

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C