Ali's vendor discovered some issues that may escalate the vendor's cost and timelines. What is the best way to proceed forward?

 A.  Sign a new contract 

B.  Follow the Change Control System 

C.  As a new SOW signed by Ali and given to the  vendor    

D. Vendor should, anyway do the additional work and invoice it to the client(Ali's Organization) 

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/06/25

Thanks for invitation - 

With the choice - B .

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

 

thanks for invition ,,,,,,,,,, my choice is option B

Mohammed Nizamul Karim
par Mohammed Nizamul Karim , Technical Officer (Tender Department) , China Railway Construction Co. LTD (CRCC)

My opinion is the right answer is: B

Ksenija Kancelak
par Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My opinion is that the right answer is:

 

D. Vendor should, anyway do the additional work and invoice it to the client(Ali's Organization)

 

Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

I prefer to leave answers to Experts. Thanks for Your kind Invitation.

Usman Islam
par Usman Islam , Yard Manager , Kirtanlal Scaffolding & Formwork

Option B is likely........

sardar mardookhy
par sardar mardookhy , PMP certified Project manager , MCCI

if the issues are included in SOW optionD

if not B.