At which stage of Inspection, is the opportunity to reduce waste the maximum? Select one:

a. At the Finished Goods stage before it is shiiped to customers

b. At the incoming material stage before the material is issues to production

c. During Work-In-Progress on the shopfloor

d. At customer place, after the finished goods are sold

user-image
Question ajoutée par Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG
Date de publication: 2016/06/17
MADAN MOHAN GAJULA
par MADAN MOHAN GAJULA , Material Coordinator , Sadara Chemical Company

b. At the incoming material stage before the material is issues to production        +++++++++++++++++

Sathish Prabhu.V
par Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

If it is a bought out finished component, then Incoming material stage reduces waste and if it is a machining casting, then Work -in Progress should reduce waste