Nicholas is the project manager of the Lidon Project. Sample testing results indicates that product?

 

  defect density is too high in compare to the upper control limit set for nthe respective matrix as part of project planning . The organization has asked Nicholas to create a chart showing the distribution of defects density against time. Which of the following is the most appropriate tool for this activity 

A.  Pareto diagram 

B.  effect of different shifts on Productivity 

C.  defect log 

D.  Control chart

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/06/09
Hrvoje Kancelak
par Hrvoje Kancelak , Certificated Traffic Engineer , Office of independent engineer

The answer is:

 

D.  Control chart

sardar mardookhy
par sardar mardookhy , PMP certified Project manager , MCCI

D is my option,

Thanks...............

Sathish Prabhu.V
par Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Control Charts are the best tools to depict the defects distribution density against time

Usman Islam
par Usman Islam , Yard Manager , Kirtanlal Scaffolding & Formwork

as the organisation is asking for chart with respect to time and frequency of defects. in my opinion Option D is best choice. 

Ksenija Kancelak
par Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My opinion is that the right answer is:

D. Control chart

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option D