A project manager has discovered a problem and is trying to determine the cause...

 

 The process whereby he identifies the variables that have the most influence on the project by holding all the variables constant and changing one at a time is called:

 

a. Product correlation b. Design of an experiment c. System integration d. Output processing

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/26
Sathish Prabhu.V
par Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Design of Experiment is the right answer.

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option B

 

sardar mardookhy
par sardar mardookhy , PMP certified Project manager , MCCI

Option B is tehanswer,

Thanks..........................

Shaik Farid
par Shaik Farid , PROJECT ENGINEER , AL HAKMIAH REAL ESTATE AND DEVELOPMENT COMPANY

option D 

Output processing

Option B is the most appropriate answer.

DOE is a form of active statistical method of improving for long-term Quality.

Usman Islam
par Usman Islam , Yard Manager , Kirtanlal Scaffolding & Formwork

option D.. i believe so...........