Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

One level above the work package that helps identify cost centers or a charge code for the purposes of project accounting is known as a what?

 

Refer to below options for answer

a. Component level

b. Control account

c. Cost breakdown structure

d. Component package

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/13
Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option B

sardar mardookhy
par sardar mardookhy , PMP certified Project manager , MCCI

B. Control Account.........................

Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

Thanks for invitation I prefer to wait for more answers .

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?