Liquidated damages for delayed completion of project recovered from subcontractor is capital receipt or revenue receipt?

user-image
Question ajoutée par Mihir Kali Bhattacharya
Date de publication: 2016/05/12
Imran khan, PMP
par Imran khan, PMP , Project Engineer/ Project Manager LV/LC , Engineering Consultants Group (ECG)

I believe that it should be kept as revenue as the the LDs are usually for delayed project completion meaning delayed operations beginning and are a compensation towards such delayed operation and lost revenue against such delay operation. Project Capital remains the same with no changes. 