Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

What is the meaning of the planning time fence?

A.  It determines the planning period for the planning run 

B.  It determines the period in which the planned orders are to be converted into production orders 

C.  It determines the period in which no automatic changes are to be made to the production plan

user-image
Question ajoutée par Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves
Date de publication: 2016/04/06
RAVISANKAR K
par RAVISANKAR K , Senior Consultant , Envecon Global Solutions Private Limited

Planning time fence don't allow any automatic changes (Ex.MRP execution) for the production plan on the determined period

Sathish Prabhu.V
par Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Option C, Not automatic changes in the production plan  in the specified period is the appropriate answer

Wasi Rahman Sheikh
par Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

Option B) is answer <<<<<<<<<<<<<<<<<<<<<<

MUBARAK INAYTULLA KHAN
par MUBARAK INAYTULLA KHAN , Procurement Manager , UNIT7 CONTRACTING EST. RIYADH.

B : IS THE CORRECT ANSWER FOR THE ABOVE QUESTION.

georgei assi
par georgei assi , مدير حسابات , المجموعة السورية

B.  It determines the period in which the planned orders are to be converted into production orders 

 

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?