Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Which software would you prefer for preparing EPC Level 3 and Level 4 Schedule. (Primavera/MS project or any other )?

user-image
Question ajoutée par Utilisateur supprimé
Date de publication: 2016/03/15
Najja Nasiif
par Najja Nasiif , Business Development Consultant , Rock of Ages Holding (U) Limited

Level 4 is an individual deliverable/document level, so for example 'Produce Test Strategy' and Level 3 is a group of deliverables, for example 'Test Documentation'

 

MS PROJECT would do

Naim Mustafa
par Naim Mustafa , Business Consultant , NC Financial Service, Inc. / Jackson Hewitt Tax

Since EPC schedule levels are normally limited to Levels 1 through 3, sometimes an ‘external’ schedule or set of schedules would be included for a project. These external schedules are called Level 4.

EPC Level 4 is detailed work schedules and generally would be prepared outside of the CPM software, with careful correlation to the CPM schedule activities and scope of work. The theory is, that if there is too much detail within the CPM network, the schedule would not only lose its flexibility as a value-added tool to manage the job, but schedule maintenance would become difficult, due to the greater effort needed to maintain the CPM logic after each progress update. A variety of software tools can be employed to develop work schedules at Level 4 and below: spreadsheets, databases, and word processing are all utilized.

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?