Is the Contractor eligible for prolongation costs, for the delays attributable to Contractors risk and responsibility in concurrent delay situation?

 

How he can claim his prolongation costs concurrent with the Employer delay

user-image
Question ajoutée par SAJI POLACHIRA , Commercial and Contracts Manager , TC Consultancy
Date de publication: 2015/10/15
Parthiban Kothandapani
par Parthiban Kothandapani , Quantity Surveyor , A Reputed Construction Company.

First no EOT can be given for Concurrent delays. Some how If the contractor awarded EOT along with concurrent delays then the contractor have a chance to claim his prolongation cost in accordance with contractual documents.

 