The level of output where a straight line drawn from the origin is tangent to the total cost curve is where?

 a. total cost is at a minimum. 

 b. average cost is equal to marginal cost. 

 c. profit is at a maximum. 

 d. all of the above are correct. 

user-image
Question ajoutée par Emad Mohammed said abdalla , ERP & IT Software, operation general manager . , AL DOHA Company
Date de publication: 2015/05/14

 

B

-----------------------------

Thanks

Alex Al Yazouri
par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

 b. >>>>>>>>>>>>>>>>>>>>>> average cost is equal to marginal cost. 

Wasi Rahman Sheikh
par Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

Answer will b >>>>>>>>>>>>>>

Emad Mohammed said abdalla
par Emad Mohammed said abdalla , ERP & IT Software, operation general manager . , AL DOHA Company

  1. The level of output where a straight line drawn from the origin is tangent to the total cost curve is where The correct answer was: b. average cost is equal to marginal cost.. average cost is equal to marginal cost. 

khaled elkholy
par khaled elkholy , HR MANAGER , misk for import & export

b. average cost is equal to marginal cost. Is correct........ ...................

i hope B will be right......as options A & C are diverting the scenario. because the tangent is drawn on that point where these two values meet and form some relationship.other wise tangent from origin to these values will not be possible.....

Bello Abubakar
par Bello Abubakar , Cinema 4D Render/Sketch UP, AutoCAD, ArchiCAD and Revit Specialist , Federal Housing Authority

B................................................

mohamed badawy
par mohamed badawy , Head Of Operations , Almajdoui Logistics Company

I CHOOSE NUMBER B ........................................................

Mohammed Fathe  Shaheem
par Mohammed Fathe Shaheem , Operation Executive , Arabian Construction Company

B....................................................

Khaled Anwar
par Khaled Anwar , Senior Sales Engineer , "Automotive company''

The answer is : Option ( B )