If RTO exceeds MAO for a certain function, what can be done to to reduce the recovery time objective to a more acceptable level?

If a recovery time objective exceeds a maximum acceptable outage for a certain function, what can be done to to reduce the recovery time objective to a more acceptable level? 

or is their any other option other than reducing the RTO??

user-image
Question ajoutée par Nancy Refai , Health, safety and environmental management Trainer and consultant , Freelancer
Date de publication: 2015/03/10
MUHAMMED HARIS MI
par MUHAMMED HARIS MI , Senior Audit Staff , Saud Bahwan Group LLC.

I agree with the Expert answer of Mrs. : Nancy Refai  .Well explained >>>>>>>>>>>>

Nancy Refai
par Nancy Refai , Health, safety and environmental management Trainer and consultant , Freelancer

If a recovery time objective exceeds a maximum acceptable outage for any function, you will need to consider mitigation strategies (for example, investing in more efficient IT disaster recovery capability) to reduce the recovery time objective to a more acceptable level, or else re-assess your risk appetite.