Explain how can the schedule performance index(SPI) Be used in schedule monitoring and control?

user-image
Question ajoutée par Ali Harin , General Manager , Harinco For Contracting And Trading Company
Date de publication: 2013/07/16
Binil Paul
par Binil Paul , Senior Planning Engineer , Keo International Consultants - Qatar

Schedule performance index SPI = BCWP/BCWS (budgeted cost for work done over budgeted cost for work planned to be done) Normally the value remains less than one.
But if you execute more value of work than that was scheduled during a particular period then you have earned more than planned costs

Anisuddin Siddiqui
par Anisuddin Siddiqui , Sr. Planning Engineer , Southwest Architecture

When the SPI <1 You are behind the schedule.
Take appropriate measures, create remedial action plan when SP =1 You are as per schedule.
When SP >1 You are performing better and completing the task earlier than planned.