A tool used to secure expert judgment? A. Peer review B. Delphi technique C. Expected value technique D. Work Breakdown Structure (WBS)

user-image
Question ajoutée par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
Date de publication: 2015/01/15

Choice (B) Delphi Technique, since it is based on consensus of decision making model

Manjusha Mohan
par Manjusha Mohan , Program Manager , Neo Technology Ltd

Delphi technique.

This communication technique relies on a panel of experts to achieve convergence of opinion on a specific issue by answering a series of questionaires.

 

Alex Al Yazouri
par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

B. Delphi technique

The Delphi technique is a commonly used tool to secure expert judgment while initiating a project.

Wolf Klaas Kinsbergen
par Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

it is called B: Delphi Technique

Vinod Jetley
par Vinod Jetley , Assistant General Manager , State Bank of India

B. Delphi technique

is the correct answer.

Divyesh Patel
par Divyesh Patel , Assistant Professional Officer- Treasury , City Of Cape Town

Answer is B

Irina Chepel
par Irina Chepel , Personal trainer , Freelancer

Thank you for the question, but must agree with others as it's not my field of expertise

VENKITARAMAN KRISHNA MOORTHY VRINDAVAN
par VENKITARAMAN KRISHNA MOORTHY VRINDAVAN , Project Execution Manager & Accounts Manager , ALI INTERNATIONAL TRADING EST.

Answer option (B) >>>>>>>>>  Delphi technique

Agree with u;   sir.

Ibrahim Hussein Mayaleh
par Ibrahim Hussein Mayaleh , Sales & Business Consultant and Trainer , Self-employed

I agree with all on the Delphi Technique

Basit Ali
par Basit Ali , Director of Engineering , Laverda Suites & Villas / Blue Bay Resorts

Opt B

Muhammad samran
par Muhammad samran , Junior Officer/Project Coordinator , Pakistan Stell Mill

The answer is B

 