Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What kinds of measures are most likely to immediately speed up Project Accomplishment?

user-image
Question added by Abdul Rehman Zaheer , Marketing & Projects Specialist , King Fahd University of Petroleum & Minerals
Date Posted: 2014/04/20
Muhammad Usman Habib
by Muhammad Usman Habib , Lead Project Engineer , Sabic - E&PM

The following measures are most likely to speed up Project Accomplishment

 

1. Focus on activiteis which are on Critical Path

2. Focus on activities which can become critical path if there is a slight delay in them

3. Crashing of activities

4. Analyzing project schedule and identifying opportunities for parrallel work without cost increase

5. Ensuring availability of all resources at job site and

6. Others.....

 

 

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.